護(hù)坡磚正確的施工流程
護(hù)坡磚的使用可以有效的防護(hù)水源對(duì)土地的侵蝕,減少路面不平整的現(xiàn)象發(fā)生。因此在很多水流附近都會(huì)有護(hù)坡磚的身影,還會(huì)在道路兩旁種上綠植,同樣護(hù)坡磚也被使用到,其獨(dú)特的結(jié)構(gòu)使得在控制水流方面非常不錯(cuò)。那么山東護(hù)坡磚的施工流程是什么呢?
The use of slope protection bricks can effectively protect the soil from water erosion and reduce the occurrence of uneven pavement. Therefore, there are slope protection bricks around many water flows, and green plants are planted on both sides of the road. Similarly, slope protection bricks are also used, and their unique structure makes them very good at controlling water flow. So what is the construction process of slope protection bricks in Shandong?
1、挖掘邊沿基坑,坑底填充適當(dāng)?shù)牟牧喜⒄饘?shí),砌筑上下沿?fù)醢?,擋板頂?biāo)高砌至與聯(lián)鎖護(hù)坡底標(biāo)高一平。
1. Excavate the edge of the foundation pit, fill the pit bottom with appropriate materials and vibrate it firmly. Build the upper and lower edge baffles, and the top elevation of the baffles shall be level with the elevation of the interlocking slope protection bottom.
2、在已經(jīng)完成的基礎(chǔ)面上鋪設(shè)土工布或者級(jí)配碎石。
2. Lay geotextile or graded crushed stone on the completed foundation surface.
3、從下邊沿開始聯(lián)鎖鋪設(shè)三行聯(lián)鎖式護(hù)坡磚,磚的長度方向沿著水流方向反向鋪設(shè),下沿..行磚有一般砌入趾墻中,與毛石或混凝土趾墻相錨固,下沿的第二行聯(lián)鎖磚的下邊沿與趾墻墻面相交。
3. Interlock and lay three rows of interlocking slope protection bricks starting from the lower edge, with the length direction of the bricks being laid in the reverse direction of the water flow direction, and the lower edge Row bricks are generally built into the toe wall and anchored to the rubble or concrete toe wall. The lower edge of the second row of interlocking bricks at the lower edge intersects the toe wall surface.
4、砌筑下沿趾墻,用混凝土或者毛石混凝土將剩余部分的趾墻連同錨固入趾墻的聯(lián)鎖磚一起砌筑,使得趾墻符合設(shè)計(jì)要求的尺寸。
4. Build the lower toe wall, and use concrete or rubble concrete to build the remaining part of the toe wall together with interlocking bricks anchored into the toe wall, so that the toe wall meets the dimensions required by the design.
5、從左下角鋪設(shè)其他護(hù)土磚,鋪設(shè)方向與趾墻平行,不得垂直趾墻方向鋪設(shè),以防產(chǎn)生累計(jì)誤差,影響鋪設(shè)質(zhì)量。
5. Lay other retaining bricks from the lower left corner in a direction parallel to the toe wall and not perpendicular to the toe wall to prevent cumulative errors that affect the laying quality.
6、將聯(lián)鎖磚鋪設(shè)至上沿墻內(nèi),砌筑上沿墻,使得上沿部分聯(lián)鎖磚與上沿墻錨固,進(jìn)行聯(lián)鎖磚面層色彩處理時(shí),清除聯(lián)鎖磚表面浮灰及其他雜物、污染,如需水洗時(shí),可用水沖洗,等水干后即可進(jìn)行色彩處理。
6. Lay interlocking bricks into the upper edge wall, and build the upper edge wall so that the upper edge part of the interlocking bricks are anchored to the upper edge wall. When conducting color treatment for the surface layer of the interlocking bricks, remove the floating ash and other debris and pollution on the surface of the interlocking bricks. If it is necessary to wash with water, it can be washed with water, and the color treatment can be carried out after the water is dry.
7、用干砂、碎石或者土填充磚孔和接縫。
7. Fill brick holes and joints with dry sand, crushed stone, or soil.
8、為形成轉(zhuǎn)角或者直邊,可用無齒鋸切割護(hù)坡磚以得到相應(yīng)的規(guī)格和角度。
8. To form a corner or straight edge, a toothless saw can be used to cut the slope protection brick to obtain the corresponding specifications and angles.
護(hù)坡磚正確的施工流程相關(guān)內(nèi)容就講解到這里了,您對(duì)此有怎樣的疑惑或者需求,就來我們網(wǎng)站http://slmachine.cn咨詢了解吧!
That's all about the correct construction process for slope protection bricks. If you have any doubts or needs about this, please come to our website http://slmachine.cn Consult and understand!
上一篇:植草磚的種草方法參考